Wind Turbine building at Rossport Solidarity Camp![]() ![]() ![]() ![]() ![]() ![]() From the 10th to 16th of August, Rossport Solidarity Camp hosted it's 3rd wind turbine building course. You can read a report of the first one here: http://www.indymedia.ie/article/95731. As the 3 previous turbines that were built are still going strong (and powering both the camp and camp house), this year it was decided to go for something bigger and more challenging. This year it's was decided to build a 4.2 metre turbine that is planned eventually to be connected to the grid at the house of a local Shell to Sea campaigner. The course which was originally scheduled to run from the 4th to the 10th August had to be delayed for 2 days after Shell go their TBM stuck, which as well as disrupting local traffic also disrupted the scheduling plans for the turbine course.. |
View Comments Titles Only
save preference
Comments (2 of 2)
Jump To Comment: 1 2..
Placing the magnet on the rotor disks
Adding the resin to make up the 2 rotor disks
Cleaning up the stator (which is made up of copper coils in resin)
..
The turbine frame on the tower head
Some finishing touches
Work also continued on a smaller turbine
Assembling the turbine for testing
Getting the blades balanced